Free SWMS template
By Stephen Billingsly · Updated
A safe work method statement (SWMS) names the high risk construction work in a job, the hazards and risks of that work, and what you will do to control them. Fill this one in for your site, print it, and have everyone doing the work sign it. Nothing you type is sent or saved.
Safe work method statement
| Your business: | Phone or email: |
| Principal contractor or builder: | Site address: |
| The job: | Date prepared: |
| Person responsible on site: | Workers consulted: |
High risk construction work in this job
None ticked.
List used: section 291 of the Work Health and Safety Regulation 2011 (Qld), the model list as Queensland made it.
The work, its hazards and the controls
| No. | The work, step by step | Hazards and risks | Control measures | How the controls are put in place and checked | Who is responsible |
|---|---|---|---|---|---|
| 1 |
How the work is checked against this document, and when it is reviewed
If the work is not being done the way this document says, it must stop as soon as it is safe to stop, and start again only once it follows this document or the document has been reviewed. Keep it until the work is finished, and for at least 2 years after a notifiable incident.
Signed by everyone doing this work
I was consulted on this document, I have read it, and I understand the hazards and the controls.
| Name | Signature | Date |
|---|---|---|
Template from extrua.com.au/tools/swms-template. The content is the business’s own.
This is general information, not legal advice. The words in a SWMS have to be yours, about your site and your work. A reload clears the form, so print or save it before you leave the page.
When the law requires a SWMS
A SWMS has to be written before high risk construction work starts. The regulations say exactly what that is. Victoria has its own regulations and a list of 19 kinds of work. The other states and territories use the national model regulations, with a list of 18.
For any other work the regulations do not ask for a SWMS, though you still have to manage the risks. Builders and commercial clients often ask for one anyway before you start on their site.
What a SWMS has to contain
Queensland’s regulation (section 299) says a SWMS must do four things.
- Identify the work that is high risk construction work.
- State the hazards of that work and the risks to health and safety that come with them.
- Describe the measures that will control the risks.
- Describe how those measures will be put in place, monitored and reviewed.
It must also take account of the circumstances at the workplace, and be set out so the people using it can understand it. Victoria’s regulation 324 asks for the same things in slightly different words. Regulators also say to name who is responsible for each control, so the template has a column for that.
The high risk construction work lists
These are the regulations’ own words. The two lists cover much the same work, worded differently. One difference: Victoria lists all demolition, while the model list names demolition of a load-bearing part of a structure.
The national model list
Section 291, Work Health and Safety Regulation 2011 (Qld). High risk construction work means construction work that:
- involves a risk of a person falling more than 2m
- is carried out on a telecommunication tower
- involves demolition of an element of a structure that is load-bearing or otherwise related to the physical integrity of the structure
- involves, or is likely to involve, the disturbance of asbestos
- involves structural alterations or repairs that require temporary support to prevent collapse
- is carried out in or near a confined space
- is carried out in or near a shaft or trench with an excavated depth greater than 1.5m, or a tunnel
- involves the use of explosives
- is carried out on or near pressurised gas distribution mains or piping
- is carried out on or near chemical, fuel or refrigerant lines
- is carried out on or near energised electrical installations or services
- is carried out in an area that may have a contaminated or flammable atmosphere
- involves tilt-up or precast concrete
- is carried out on, in or adjacent to a road, railway, shipping lane or other traffic corridor that is in use by traffic other than pedestrians
- is carried out in an area at a workplace in which there is any movement of powered mobile plant
- is carried out in an area in which there are artificial extremes of temperature
- is carried out in or near water or other liquid that involves a risk of drowning
- involves diving work
Victoria
Regulation 322, Occupational Health and Safety Regulations 2017 (Vic). High risk construction work means any of the following construction work:
- where there is a risk of a person falling more than 2 metres
- on telecommunications towers
- involving demolition
- involving the removal or likely disturbance of asbestos
- involving structural alterations that require temporary support to prevent collapse
- involving a confined space
- involving a trench or shaft if the excavated depth is more than 1.5 metres
- involving a tunnel
- involving the use of explosives
- on or near pressurised gas distribution mains or piping
- on or near chemical, fuel or refrigerant lines
- on or near energised electrical installations or services
- in an area that may have a contaminated or flammable atmosphere
- involving tilt-up or precast concrete
- on or adjacent to roadways or railways used by road or rail traffic
- at workplaces where there is any movement of powered mobile plant
- in an area where there are artificial extremes of temperature
- in, over or adjacent to water or other liquids where there is a risk of drowning
- involving diving
A template is a start, not the document
A SWMS copied from somewhere else and signed without reading is the thing regulators warn about. WorkSafe Victoria says a generic SWMS has to be reviewed on site, has to cover all the high risk work and risks of the job, and should have anything not relevant to the site removed. This template gives you the headings and the lists. The steps, hazards and controls are for you and your crew to write, standing where the work will happen.
Once it is written
Follow it. If the work is not being done the way the SWMS says, the work has to stop as soon as it is safe to stop, and start again only in line with the SWMS. Victoria’s regulation lets work resume once the SWMS is complied with or has been reviewed and revised.
Give the builder a copy. Under Queensland’s regulation, on a construction project (one where the construction work costs $250,000 or more) the principal contractor must get a copy before the high risk work starts.
Review it when things change. Victoria’s regulation says to review it whenever the high risk work changes, or when there is a sign the controls are not working, including after any incident.
Keep it where the crew can read it. Queensland’s regulation says to keep it until the work is finished, to keep it at least 2 years after a notifiable incident, and to have a copy readily accessible to the workers doing the job. Victoria’s says to keep it for the duration of the work.
Signed on the phone, not in the ute
In Extrua Dispatch you upload each SWMS once. Every worker signs it on their phone, and signs again when you issue a new version. It is free on every plan.
Check your own state
This page was checked on 14 November 2026 against Queensland’s Work Health and Safety Regulation 2011 and Victoria’s Occupational Health and Safety Regulations 2017. Safe Work Australia says the model laws are in force in every state and territory except Victoria, and that a state can vary them. Your regulator has the rules for where you work.